Hi Craig,
Yes I agree to it....that it wud have caused snowball effect if the requirements would have gone into implementations.........if such thing happens, many a timesproject enter into denger zone........I also agree to it......It was not sheer wastage of time( Actually we were hundreds of miles away from our project plan !! ...2 weeks work took 4 weeks.....) ...as it tought us very valueable lessons........The lessons learnt session was having many points dealing with this sceene....
Morals I learnt out of this
1. First try to map your objectives/end output of the system with your actual input data provided(although its raw data it should give a base to go for further stages)
Always try to MAP whether you have things in store fwhich your customer would like to buy....Non Realistic CAN DO attitude doesn't help !
2. Always check whether the communication has any leak......here it was limited mob......if yes try to get things clarified first....who all are involved..why other ppl
are not involved.
3. We should have stakeholder matrix .....having all the stake holders involved.....their stakes in sucesss/failure of project....their power to
approve/deny/authenticate decision. Surely Idea should be coming from everybody....they are appreciated, but the decision should be coming from authority.
4. Try to get clarifications for whatever you think is in gray area.....the more you keep them in gray area....the more they produce other If's and but's scenario.
I am sure there would be many more lessons with this, primarily I can see these for sure.
thanks,
Priyanka